UPDATE: As per Vans recommendation I started building the right elevator first, as it is not as complicated as the LH elevator.

Results came out very good. Just need to fit the fiberglass fairings, but that I will only do when I have nothing else to do (whilst waiting for delivery of the wing kit...)

Now I will start the LH elevator..

Pics below
You do not have the required permissions to view the files attached to this post.
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: The long journey began

Unread post by Induna »

just another comment... i invested in a pneumatic rivet/dimple squeezer and it it TOTALLY worth its money!!! with the hand squeezer I had constant joint pains for days.. lol

It makes the task so much more enjoyable... =D>
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
Goose1
Frequent AvComer
Posts: 977
Joined: Sun Sep 20, 2009 3:20 pm
Closest Airfield: FAWB
Location: Pretoria, FAWB
Has thanked: 182 times
Been thanked: 196 times

Re: RV-8 BUILD: The long journey began

Unread post by Goose1 »

Hi J

For interest do the elevators come with the plates to do SB14-02-05. We have a RV8 with crakes at the top rudder hinge and loose rivets on the elevator outboard hinges. We are fitting the plates now.

Groete
You do not have the required permissions to view the files attached to this post.
Hans de Beer
AME A and H
PPL A and H
RV8 ZU-KEA
Aviat Husky ZS-MEN
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: The long journey began

Unread post by Induna »

Goose1 wrote: Mon Jul 30, 2018 8:25 pm Hi J

For interest do the elevators come with the plates to do SB14-02-05. We have a RV8 with crakes at the top rudder hinge and loose rivets on the elevator outboard hinges. We are fitting the plates now.

Groete
Hi Hans,

no i do not have the doublers. I see that the SB is only applicable where cracks are already found:
NOTE: Installation of this service bulletin as preventative maintenance is not
recommended. If cracking has occurred at an outboard hinge position, install a
doubler only at that position.
The elevator kit i have does have the spar reinforcing plates though. Are there kits that did not have them?

Jacques
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
Goose1
Frequent AvComer
Posts: 977
Joined: Sun Sep 20, 2009 3:20 pm
Closest Airfield: FAWB
Location: Pretoria, FAWB
Has thanked: 182 times
Been thanked: 196 times

Re: RV-8 BUILD: The long journey began

Unread post by Goose1 »

Induna wrote: Mon Jul 30, 2018 8:37 pm
Goose1 wrote: Mon Jul 30, 2018 8:25 pm Hi J

For interest do the elevators come with the plates to do SB14-02-05. We have a RV8 with crakes at the top rudder hinge and loose rivets on the elevator outboard hinges. We are fitting the plates now.

Groete
Hi Hans,

no i do not have the doublers. I see that the SB is only applicable where cracks are already found:
NOTE: Installation of this service bulletin as preventative maintenance is not
recommended. If cracking has occurred at an outboard hinge position, install a
doubler only at that position.
The elevator kit i have does have the spar reinforcing plates though. Are there kits that did not have them?

Jacques
Yes the plates must only be fitted were cracks are found, was just wondering if they changed the design.
Hans de Beer
AME A and H
PPL A and H
RV8 ZU-KEA
Aviat Husky ZS-MEN
User avatar
Chalkie
Too Tousand
Too Tousand
Posts: 2939
Joined: Mon Jun 02, 2008 9:19 am
Closest Airfield: Tranquility
Location: Tranquility
Has thanked: 736 times
Been thanked: 1692 times

Re: RV-8 BUILD: The long journey began

Unread post by Chalkie »

Goose1 wrote: Mon Jul 30, 2018 9:42 pm The elevator kit i have does have the spar reinforcing plates though. Are there kits that did not have them?

Jacques
Yes the plates must only be fitted were cracks are found, was just wondering if they changed the design.
[/quote]

Hang on guys, there seems to be some confusion here. The elevators and rudder spars have always had the doublers (on all RV variants) where the Heim joint screws into the K1000-6 anchor nut. The spar cracking is associated with misalignment of pivot centres, loose jam nuts and perhaps aerobatic loads. The repair is relatively simple with the addition of a .063" doubler on the outer face.

I have found many RV-s with the jam nuts loose, this puts all elevator loads onto the two rivets holding the anchor nut. The flexing causes the spar to crack.

I took an old open end spanner, heated it with oxy/acetylene and bent two 90 degree offsets so that the spanner fits flat on the spar and clears the spar flanges. This allows me to tighten the nuts properly.

The picture posted by Goose1 above is a good example of loose jam nuts and all the loads being applied to the rivets holding the anchor nut, which causes stress cracks in the spar web.

I will post a picture later.
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: The long journey began

Unread post by Induna »

Chalkie wrote: Wed Aug 01, 2018 8:18 am

Hang on guys, there seems to be some confusion here. The elevators and rudder spars have always had the doublers (on all RV variants) where the Heim joint screws into the K1000-6 anchor nut. The spar cracking is associated with misalignment of pivot centres, loose jam nuts and perhaps aerobatic loads. The repair is relatively simple with the addition of a .063" doubler on the outer face.

I have found many RV-s with the jam nuts loose, this puts all elevator loads onto the two rivets holding the anchor nut. The flexing causes the spar to crack.

I took an old open end spanner, heated it with oxy/acetylene and bent two 90 degree offsets so that the spanner fits flat on the spar and clears the spar flanges. This allows me to tighten the nuts properly.

The picture posted by Goose1 above is a good example of loose jam nuts and all the loads being applied to the rivets holding the anchor nut, which causes stress cracks in the spar web.

I will post a picture later.
Hi Chalkie

this makes perfect sense, thanks. Yes I have checked and my kit does have the spar reinforcement plates on the inside of the spar. I have added a note to self to make sure of the jam nut tightness. Also, your spanner idea is great to ensure that the spanner face is flat against the spar when tightening.
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
User avatar
Chalkie
Too Tousand
Too Tousand
Posts: 2939
Joined: Mon Jun 02, 2008 9:19 am
Closest Airfield: Tranquility
Location: Tranquility
Has thanked: 736 times
Been thanked: 1692 times

Re: RV-8 BUILD: The long journey began

Unread post by Chalkie »

If you look at the photo below you will see cracking of the spar web under the heads of the rivets that hold the anchor nut.

I built my RV-6 to plans, but found the heads of the rivets interfered with the bent spanner I made; so on all builds after that, the AN470AD4-4 rivets were replaced with AN426AD4-4 The spar can be dimpled to accept the counter-sunk rivet head and the .063" doubler can be machine countersunk so that the anchor nut sits flat on the doubler.

http://avcom.co.za/phpBB3/download/file ... &mode=view
User avatar
Chalkie
Too Tousand
Too Tousand
Posts: 2939
Joined: Mon Jun 02, 2008 9:19 am
Closest Airfield: Tranquility
Location: Tranquility
Has thanked: 736 times
Been thanked: 1692 times

Re: RV-8 BUILD: The long journey began

Unread post by Chalkie »

A .jpeg of the modified set spanner...
Attachment-1.jpeg
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: The long journey began

Unread post by Induna »

Chalkie wrote: Sun Aug 05, 2018 9:40 am A .jpeg of the modified set spanner...

Attachment-1.jpeg
Thanks Chalkie! a very good piece of information for all!
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: Empennage almost complete - wing kit ordered

Unread post by Induna »

UPDATE: The empennage kit is almost complete with only the fiberglass fairings remaining. I also took the step and ordered the wing kit (slow build).

While I am waiting for the kit to arrive I started building another double garage, which will be my primary workshop, as space will becoming an issue very soon... Luckily I need the garage in future, so its not an unnecessary expense... =D>
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
Thatch
Straight and Level
Posts: 243
Joined: Tue Feb 27, 2007 3:38 pm
Closest Airfield: Lanseria
Location: Honeydew Ridge
Has thanked: 1 time
Been thanked: 26 times

Re: RV-8 BUILD: The long journey begins (ALMOST)

Unread post by Thatch »

Induna wrote: Thu Mar 15, 2018 4:55 pm

I am a taildragger fan (and most of my hours are TD), so naturally I will build the TD version. (i think it's wrong to build a tri-gear RV-8... :roll: )

J
I saw nose wheel RV8's for the first time at Oshkosh this year and I must say that they just look wrong.
User avatar
Chalkie
Too Tousand
Too Tousand
Posts: 2939
Joined: Mon Jun 02, 2008 9:19 am
Closest Airfield: Tranquility
Location: Tranquility
Has thanked: 736 times
Been thanked: 1692 times

Re: RV-8 BUILD: Empennage almost complete - wing kit ordered

Unread post by Chalkie »

Just a follow up on the picture of the modified set spanner to tighten the jam nut.

I also took a bit of 7/8" 4130 pipe with .040" wall thickness and squared off the one end to allow me to use it to screw in the rod end bearings / Heim joints.
Attachment-1.jpeg
To insert these rod ends to the correct length, Van gives a measurement from the spar web to the bolt centre, great for design engineers but with a self aligning spherical bearing this is difficult to measure. So take the value given and convert it to mm then add half of the outer diameter of the rod end bearing housing (6 of the 7 are 19mm diameter) then add this to the bolt-centre value and make a tool from ally scrap. Now you can set all rod end bearings to the correct value for elevator or rudder alignment.
Attachment-1.jpeg
Take note, the four rivets around the rod end are AN426AD4-5 and not AD470 as called for in the plans. I find the round heads of theAN470 rivets get in the way when trying to tighten the jam nuts
Attachment-1.jpeg
User avatar
Induna
1k poster
1k poster
Posts: 1979
Joined: Tue Mar 20, 2012 10:01 am
Closest Airfield: FASD
Location: Port Owen - Western Cape
Has thanked: 150 times
Been thanked: 184 times

Re: RV-8 BUILD: Empennage almost complete - wing kit ordered

Unread post by Induna »

UPDATE: the manufacturing of my wingkit is complete. It is now being crated and will subsequently ship early November. Hopefully I will have it delivered before the end of December...

Also my new workshop (newly build double garage) has been completed, so now I will have sufficient space for the bigger sub-kits to be built...

Good times ahead.
Jacques van der Westhuizen
ZS-WSW | Sonerai 2L
ZU-FBA | Sonex Aircraft Waiex
User avatar
Fransw
Niner Tousand
Niner Tousand
Posts: 9156
Joined: Tue Jun 02, 2015 3:22 pm
Closest Airfield: Pretoria
Location: Pretoria
Has thanked: 1439 times
Been thanked: 974 times

Re: RV-8 BUILD: Empennage almost complete - wing kit ordered

Unread post by Fransw »

Nice one! You are making good progress! :D